Cabinets delivered & Staircase goes in

Rocking along now. Kitchen cabinets have been delivered and the installation begins


Same for the Butler's Pantry


Carpenter installing the upgraded staircase


Cabinets for Bed 5 Ensuite


Wednesday, 10 May 2017

Gyprock Goes on - in record time!

The gyprockers turned up on Saturday and tooled up to the max, pretty much finished in 3 days












Saturday, 6 May 2017

Insulation goes in

Metricon installed all of the R4 & R2 insulation before the gyprock goes on










Driveway is finished!!

Been waiting a few days but well worth the wait. They've extended it around to the front door as well which is great news. This is the s...